Solisterra Homes
Call

Build season

The slab-on-grade is poured during the 6-week factory build. Outside the comfortable window, a pour can still go ahead with cold-weather protection, at extra cost. A slab is never placed on frozen ground.

RegionLast spring frostFirst fall frostComfortable pour windowFrost depthOrder by
Ottawa / GatineauMay 9Oct 12mid-May → mid-Oct~1.5 mAug 24
GTA (Toronto)Apr 20Nov 1late Apr → end Oct~1.2 mSep 13
GTA west (Mississauga / Hamilton)Apr 20–25Oct 28late Apr → late Oct~1.2 mSep 9
LondonApr 22Oct 18late Apr → mid-Oct~1.2 mAug 30
WindsorApr 20Oct 28late Apr → late Oct~1.2 mSep 9
BarrieMay 21Sep 24late May → late Sep~1.5 mAug 6
SudburyMay 31Sep 17June → mid-Sep~1.8 mJul 30
MontréalMay 9Oct 7mid-May → early Oct~1.2–1.5 mAug 19
Québec CityMay 17Sep 28late May → late Sep~1.6 mAug 10

Frost dates are ECCC 1991–2020 normals (50th percentile) via GrowersGuide. Frost depths are secondary sources: confirm them with the building department. The comfortable window is our heuristic, between average last and first frost, not a code limit. Order-by dates are the first-frost date minus 7 weeks. In practice, apply for permits in spring.

Order-by planner

Order at least 7 weeks before you want the home installed: 6 weeks to build and 7 days to install. The slab is poured during the factory build.

Order by July 14, 2027

The pour falls inside this region's comfortable window (a planning heuristic, not a code limit).